During a recent government meeting, discussions centered on the status of a preliminary work agreement for a traffic study in West Fargo. City Engineer Dan Hansen provided an update, indicating that the agreement aims to hire a consultant to evaluate three potential traffic entry options for a specific site.
The proposed options include a U-turn on 40th Avenue, extending a lane on the south side of 40th, and the possibility of a roundabout at the intersection of 4th and 40th, as recommended by the Planning Commission. Hansen noted that the preliminary work agreement has been in progress since November of the previous year but is currently on hold due to a zoning violation issue.
The outcome of this traffic study is contingent upon the resolution of the zoning violation, which must be addressed before any further action can be taken. The discussions highlight the city's ongoing efforts to improve traffic management and infrastructure planning in response to community needs.