In a recent Oak Park village board meeting, officials discussed a significant amendment to the redevelopment agreement for the Madison Street project, which includes the highly anticipated Pete's Market. The board approved a sixth amendment to the agreement, which introduces several notable changes aimed at addressing ongoing frustrations related to the project's delays.
Key updates in the amendment include the addition of electric vehicle charging stations, a $22,000 donation to the Oak Park Area Arts Council for temporary public art, and a reduction in financial incentives by $100,000. Furthermore, the amendment establishes stricter performance penalties, including monthly payments of $16,000 if construction is not under roof within nine months, and $45,760 if a certificate of occupancy is not obtained within 16 months.
Development Services Director Emily Leegan provided an update on the permit status, indicating that a permit application for the earth retention system and building shell was submitted on June 7. The latest round of corrections was approved, and the permit could be picked up as soon as the required fee of $157,377 is paid.
Trustee members expressed their frustrations regarding the prolonged timeline and lack of communication from Pete's representatives. Trustee Enya highlighted the community's dissatisfaction, emphasizing the need for more transparent communication moving forward. In response, Pete's representatives acknowledged the challenges faced, including the loss of their architect, which contributed to the delays.
The board also discussed the clawback provisions in the agreement, which allow the village to reclaim the property if project deadlines are not met. While some members expressed concerns about the scope of these provisions, Pete's representatives reassured the board of their commitment to completing the project, citing significant financial investments already made.
As the meeting concluded, the board reiterated the importance of maintaining open lines of communication to foster a productive partnership with Pete's, aiming to ensure the successful completion of the Madison Street redevelopment project.