The Everett City Council held a special meeting on March 13, 2024, to discuss the urgent need for a roof replacement project at a local building, with a proposed budget of $11.4 million. The meeting focused on the timeline and financial implications of the project, emphasizing the necessity of securing funding and moving forward promptly to avoid increased costs.
The discussion began with a presentation outlining the project timeline, which aims to commence demolition on June 24, 2024, following the end of the school year. City officials stressed the importance of securing funding and contractor bids by early March to ensure materials and labor are available at current prices. Delays could lead to higher costs and potential postponement of the project until the following year, as winter conditions would hinder construction efforts.
Consultants involved in the project highlighted the complexity of the roof replacement, noting that it involves multiple trades and logistical challenges. They expressed concern that missing the bidding window could result in fewer available contractors and increased project costs.
Council members voiced their apprehensions regarding the financial burden on taxpayers. One councilor questioned the implications of borrowing $11.4 million, seeking clarity on how it would affect the city’s debt and tax rates. The city’s financial officer indicated that annual payments for a 20-year bond at current interest rates would be approximately $838,000, with a total interest cost of around $5 million.
The meeting also featured discussions about the building's condition, with some councilors expressing frustration over the lack of transparency regarding the building's overall needs. They emphasized the importance of understanding the full scope of necessary repairs beyond the roof, particularly concerning the third and fourth floors.
As the meeting progressed, council members expressed a desire for more comprehensive information before making a decision. A motion was made to postpone the vote to allow further evaluation of the building's condition and potential impacts on the community.
In conclusion, the Everett City Council's special meeting underscored the urgency of the roof replacement project while highlighting the financial considerations and community concerns that must be addressed before proceeding. The council plans to reconvene for further discussions to ensure a well-informed decision that balances the city's needs with fiscal responsibility.