In the heart of Brownsburg, Indiana, the City Council convened to address pressing issues surrounding the construction activities at the Eagle Creek Logistics Park. The meeting, held on March 19, 2025, focused on a contentious stop work order affecting Fiber Global, a company seeking to transform an existing building into a manufacturing facility for high-quality fiberboard.
The discussion began with a detailed overview of the situation by city staff, who explained that the stop work order was issued after the fire marshal observed unauthorized construction activities on-site. This order, rooted in the municipal code and unified development ordinance, halted all work until proper permits were secured. The staff emphasized that the tenant finish permit, essential for the completion of the building's interior, had not yet been issued, leaving the project in limbo.
Before you scroll further...
Get access to the words and decisions of your elected officials for free!
Subscribe for Free As the meeting progressed, it became clear that the timeline of events was complex. Following the initial stop work order in October, the city had engaged in numerous communications with Fiber Global to clarify the necessary documentation for their remodel. Despite these efforts, the required details were not adequately provided, leading to a second stop work order in January after a fire incident linked to ongoing construction activities.
Legal representatives for Fiber Global, including Joanne Sommer and Ali Sylvia, presented their case, expressing frustration over the delays and the implications of the stop work order on their operations. They argued that the facility would play a crucial role in recycling waste materials into valuable products, thus contributing positively to the community.
City staff, however, maintained that the stop work order was essential for ensuring safety and compliance with building regulations. They highlighted that reversing the order would serve no purpose without the necessary permits in place, reiterating their recommendation to affirm the stop work order.
As the council deliberated, the tension between regulatory compliance and economic development was palpable. The outcome of this meeting could significantly impact Fiber Global's operations and the broader economic landscape of Brownsburg. With the council's decision pending, the community watches closely, aware that the resolution of this issue could set a precedent for future industrial developments in the area.