The Olivette City Council meeting on March 31, 2025, highlighted significant developments in the ongoing project at Lot 1 and Lot 2, which has been a focal point for the community since its inception. The council discussed the completion timeline for the project, which has faced delays but is now nearing its final stages.
The project, originally approved in 2015 with a vision for an 85,000 square-foot development costing around $35 million, has seen costs soar to over $85 million due to various challenges. Developer Greg Yawitz addressed the council, explaining that the delays stemmed from extensive site work, including a $2 million investment to widen Olive Boulevard to alleviate traffic concerns. This work was complicated by the simultaneous development of a nearby Costco, which required additional road modifications.
Yawitz noted that the project faced further setbacks due to regulatory hurdles, including a lengthy permitting process with the U.S. Army Corps of Engineers to encase a navigable tributary on the site. The COVID-19 pandemic also played a significant role, impacting material costs and labor availability.
Despite these challenges, Yawitz expressed optimism about the project's outcome, particularly the addition of an Aldi grocery store, which was a key request from the council and the community. The grocery store is expected to enhance local access to food and contribute positively to the community's needs.
As the council prepares to engage with the developer about the project's status, they anticipate reaching 100% completion by mid-2025. This development is seen as a crucial step in revitalizing the area and meeting the community's demands for essential services. The council's commitment to supporting this project reflects their dedication to improving the quality of life for Olivette residents.