The City of Mount Pleasant, Texas City Council convened on November 5, 2024, to address several key agenda items, including a significant settlement agreement with KSA Engineers, Inc. regarding the replacement of raw water transfer pumps at the Bob Sandlin Water Treatment Plant.
The meeting began with a discussion led by the Mayor concerning the settlement reached with KSA Engineers. The settlement involves KSA agreeing to replace two raw water transfer pumps and motors at the treatment plant. In return, the city will release any claims against KSA related to this specific issue, while maintaining the right to pursue other claims in their ongoing relationship.
The settlement agreement, which was included in the meeting packet, outlines that KSA will not only install the new pumps but will also provide a warranty for the electrical workmanship. Additionally, KSA will make commercially reasonable efforts to transfer a 12-month manufacturer's warranty covering the pumps and motors to the city.
The council reviewed the terms negotiated with KSA's legal counsel, confirming that all parties have signed off on the agreement, which is now ready for the city's approval.
In conclusion, the council's meeting highlighted the collaborative efforts between the city and KSA Engineers to ensure the operational integrity of the Bob Sandlin Water Treatment Plant while also addressing legal claims in a manner that preserves their ongoing partnership. Further steps will involve formal approval of the settlement agreement in the upcoming sessions.