Moore Engineering updates Wilton council on wastewater and water system projects

November 13, 2024 | Mobridge, Walworth County, South Dakota


This article was created by AI summarizing key points discussed. AI makes mistakes, so for full details and context, please refer to the video of the full meeting. Please report any errors so we can fix them. Report an error »

Moore Engineering updates Wilton council on wastewater and water system projects
The Mobridge City Council meeting on November 13, 2024, highlighted significant developments in local water and wastewater projects, with a focus on ongoing construction and necessary change orders.

Jared Clubundi from Moore Engineering provided updates on several key initiatives, including the wastewater treatment plant rehabilitation and the water system projects. He reassured council members that warranty work on the treatment plant was progressing, with no costs to the city. However, he noted delays due to manufacturer warranty issues related to coating failures.

A major point of discussion was the biological assessment for the water intake project, which identified potential habitats for three threatened species. Clubundi explained that while no species were observed, construction may require monitoring to avoid disrupting nesting areas, pending FEMA's approval of the assessment.

The council also reviewed the water tank project, where foundation work has commenced. Clubundi indicated that the tank's construction would begin in spring 2025, contingent on weather conditions. He emphasized the importance of completing groundwork before winter to avoid complications in the spring.

Several change orders were proposed and approved during the meeting. The council authorized a change order to widen a ramp at the water treatment plant for $3,351.44, enhancing accessibility for snow removal. Additional change orders included replacing outdated piping for $3,889.36 and adding a drainage feature for $6,031.46 to prevent freezing issues in the system.

The council also discussed the timeline for the water treatment plant project, adjusting the completion date to March 2026 to allow for equipment delays. This change aims to ensure construction occurs during lower water usage periods, minimizing disruption.

In a proactive move, the council considered granting staff authority to approve minor change orders to expedite decision-making during construction, reflecting a strategy to maintain project momentum without unnecessary delays.

Overall, the meeting underscored the city's commitment to improving its water infrastructure while navigating environmental considerations and logistical challenges. The council's decisions are expected to facilitate smoother project execution and enhance service reliability for Mobridge residents.