Shannon Wells outlines Stridman Road traffic analysis and construction plans

April 22, 2025 | Madison County, Mississippi

Thanks to Scribe from Workplace AI , all articles about Mississippi are free for you to enjoy throughout 2025!


This article was created by AI using a video recording of the meeting. It summarizes the key points discussed, but for full details and context, please refer to the video of the full meeting. Link to Full Meeting

The Madison County government meeting on April 22, 2025, focused on the ongoing developments for Stribling Road, specifically the section from Highway 463 to Dewees Road. Shannon Wells from Garver Engineering provided an update on the project, highlighting key findings from recent traffic analyses and geotechnical assessments.

Wells reported that a traffic study has been completed, indicating a need for improvements at the Camden Crossing intersection. Options being considered include the installation of a traffic signal or a roundabout to better manage congestion, particularly during peak hours when parents drop off their children at Mansdale School. The proposed design includes a continuous five-lane section, which aims to alleviate current traffic issues, although some queuing remains a concern.
final logo

Before you scroll further...

Get access to the words and decisions of your elected officials for free!

Subscribe for Free

The engineering team is also exploring a potential modification to the design, suggesting a transition from a five-lane to a three-lane section on the western end of the project. This change is under consideration due to factors such as cost and constructability, with further discussions planned in the coming weeks.

Wells addressed geotechnical challenges, noting that much of the material along the proposed route is unsuitable for road construction. This will necessitate undercutting and backfilling, which could increase project costs. The team is also preparing for upcoming meetings with utility companies to discuss the relocation of overhead power lines, a critical step in the project timeline.

Family Scribe
Custom Ad
Looking ahead, the environmental report is complete, and preliminary design work is set to advance. The team aims to begin title work for affected parcels soon, as they have identified many properties that will be impacted by the project. The overall schedule has been adjusted to expedite certain phases, with the goal of moving towards the bidding process in the near future.

In conclusion, the meeting underscored the importance of addressing traffic flow and infrastructure challenges on Stribling Road, with ongoing evaluations and community engagement expected to shape the project's next steps.

Converted from Stribling Road from Hwy 463 to Dewees Road Garver Engineering meeting on April 22, 2025
Link to Full Meeting

Comments

    View full meeting

    This article is based on a recent meeting—watch the full video and explore the complete transcript for deeper insights into the discussion.

    View full meeting

    Sponsors

    Proudly supported by sponsors who keep Mississippi articles free in 2025

    Scribe from Workplace AI
    Scribe from Workplace AI