Blacktail Dam project bids come in under budget as scope adjustments made

April 15, 2025 | Williams County, North Dakota

Thanks to Scribe from Workplace AI , all articles about North Dakota are free for you to enjoy throughout 2025!


Blacktail Dam project bids come in under budget as scope adjustments made

This article was created by AI using a video recording of the meeting. It summarizes the key points discussed, but for full details and context, please refer to the video of the full meeting. Link to Full Meeting

The Williams County Park Board convened on April 15, 2025, to discuss the progress and financial aspects of the Blacktail Dam project. The meeting focused on the recent bidding process, budget adjustments, and project scope.

The discussion began with an overview of the current bidding climate, highlighting that many projects are coming in under budget despite ongoing economic challenges such as inflation, high interest rates, and labor shortages. The board noted a significant number of bids received—approximately 40 to 45 across various scopes of work—indicating strong participation from subcontractors and trade partners in the Western North Dakota market.

As the meeting progressed, it was revealed that initial estimates for the project were around $11.7 million, exceeding the allocated budget for Blacktail Dam. In response, the design team implemented cost-saving measures, successfully reducing the budget to approximately $10.6 million. This adjustment was achieved by cutting about $1.1 million from the project scope, which included the community building that was not aligned with the county's programming needs.

The board also discussed the identification of bid alternates, which serve as a contingency to add back elements to the project if the final costs allow. The base bid, without any alternates, was reported to be just under $9.1 million, which was viewed positively by the board as it allows for potential allocation of funds to other projects.

The meeting concluded with a review of the cost summary, emphasizing that all recommended bids were from the lowest bidders, ensuring fiscal responsibility. The board expressed confidence in the project's direction and the ability to deliver a comprehensive park experience while remaining within budget constraints. Further updates will be provided as decisions on the bid alternates are finalized.

Converted from Williams County Park Board - Apr 15 2025 meeting on April 15, 2025
Link to Full Meeting

Comments

    View full meeting

    This article is based on a recent meeting—watch the full video and explore the complete transcript for deeper insights into the discussion.

    View full meeting

    Sponsors

    Proudly supported by sponsors who keep North Dakota articles free in 2025

    Scribe from Workplace AI
    Scribe from Workplace AI