In a recent meeting of the Water Resources Board in Murfreesboro, Tennessee, city officials discussed significant developments regarding a long-term water and sewer project. The project, which spans four miles, has faced delays due to underestimations in the design process, particularly concerning new subdivisions that have emerged in the northern section of the area.
City representatives highlighted that the Tennessee Department of Transportation (TDOT) had not accounted for these new developments in their initial surveys. As a result, adjustments to the design were necessary to accommodate the updated drainage systems and sewer provisions. This has led to a need for revisions in easement descriptions and exhibits, which are currently being coordinated with the city’s legal team.
Before you scroll further...
Get access to the words and decisions of your elected officials for free!
Subscribe for Free The urgency of the project was underscored by the desire to bid it out in the fall. Officials noted that TDOT is expected to submit final plans in April, which will include a comprehensive review to ensure that all utility designs are compatible. Once finalized, contracts for utility relocations, including water and sewer, will be presented for approval.
The meeting also addressed the financial implications of these changes, with additional engineering costs amounting to $87,050.50, bringing the total project cost to approximately $606,000. The board members moved swiftly to approve the necessary actions, indicating a commitment to advancing the project despite the challenges.
As the city navigates these complexities, the focus remains on ensuring that the infrastructure can adequately serve the growing community, with easements expected to be acquired and recorded before the bidding process begins. The discussions reflect a proactive approach to urban development and resource management in Murfreesboro, setting the stage for future improvements in the city’s water and sewer systems.