The Woodford County Fiscal Court meeting on April 22, 2025, focused on significant developments in local infrastructure projects, particularly a major fiber optic installation. The meeting featured a presentation by a representative from a project funded by the Kentucky Broadband Initiative Program (KBIP), who outlined the progress and future steps for the fiber project.
The representative reported that the project is currently underway, with a dedicated FAQ webpage set to launch soon. This page will serve as a resource for residents, allowing them to submit questions and receive updates about the project. The team is currently conducting an environmental review, a necessary step before construction can fully commence.
Before you scroll further...
Get access to the words and decisions of your elected officials for free!
Subscribe for Free As part of the project, field personnel will begin assessing the planned routes for the installation of 84 miles of fiber optic cable. This preliminary work will involve driving the designated routes to ensure that the plans are feasible and to make any necessary adjustments. The representative emphasized the importance of keeping the community informed to avoid surprises, particularly regarding the presence of construction vehicles.
The project is on a tight timeline, with a completion deadline set for December 31, 2026. The team plans to expedite the process by overlapping various phases of the project, aiming to provide service to customers as soon as possible, rather than waiting for the entire installation to be completed. The representative expressed enthusiasm for the project and the positive impact it will have on the community, promising to keep residents updated throughout the construction phase.
In addition to the fiber project, Casey Smith from the District 7 office of the Department of Highways also presented on the rural secondary program, indicating ongoing efforts to improve local road infrastructure.
Overall, the meeting highlighted the county's commitment to enhancing connectivity and infrastructure, with officials eager to engage with the community as these projects progress.