Brighton City Council held a study session on May 13, 2025, focusing on significant updates regarding the water treatment plant and Lutz Reservoir projects, both of which are crucial for the city's infrastructure and water management.
City Manager Martinez introduced the session, highlighting the upcoming tours of the water treatment plant and Lutz Reservoir scheduled for May 27. Director Olsen provided a detailed update on the water treatment plant, showcasing progress through a series of images. The project is currently ahead of schedule by 46 days, with substantial completion expected by December 2026. Key developments include the installation of filter basins and treatment process tanks, with major equipment deliveries anticipated soon.
Financially, the project has seen five change orders, with the most recent adjustments ensuring that costs remain manageable. The council was reassured that the project timeline aligns with state regulations regarding operational deadlines.
The discussion then shifted to the Lutz Reservoir, which is also progressing well, with a completion date set for March 2026, two months ahead of schedule. The reservoir will feature non-potable distribution pipes and regional trails, enhancing community access to the area. The council discussed the reservoir's capacity, estimated at around 40 acres of surface water.
In addition to these updates, the council reviewed an intergovernmental agreement amendment concerning the South Outfall drainage system. This amendment will allocate additional funds for ongoing projects aimed at improving storm drainage and addressing sedimentation issues caused by nearby farming operations. The city plans to explore recreational opportunities along the South Outfall corridor, potentially transforming it into a community amenity.
Overall, the meeting underscored the city's commitment to enhancing its water infrastructure and addressing community needs through proactive planning and development. The council's next steps will involve approving the necessary resolutions to continue these vital projects.