The Pitkin County Board of County Commissioners (BOCC) held a work session on May 22, 2025, to discuss significant developments regarding the airport's renovation and expansion projects. The meeting focused on timelines, budgeting, and community impacts associated with the upcoming construction phases.
The session began with discussions on the demolition phase of the airport project, with officials expressing optimism about starting as early as April, depending on weather conditions. It was noted that while construction activities may be hindered by inclement weather, demolition could proceed effectively. The timeline aims to align with the closure of ski slopes, allowing for a smoother transition into construction.
Before you scroll further...
Get access to the words and decisions of your elected officials for free!
Subscribe for Free A key topic was the potential bonding question for funding, which remains under consideration for this year. The board is evaluating options that may not involve tax increases, including a home rule charter amendment. The urgency of these discussions was emphasized, as decisions made now will significantly impact the project's timeline and community engagement.
The commissioners also addressed the possibility of completing the project in one season versus extending it over two years. Concerns regarding light and noise pollution were raised, highlighting the need for careful planning to mitigate community disruption. The board agreed to further explore these considerations as the project progresses.
Moving on to the terminal project, officials reported that the design selection process is underway, with a contract expected to be negotiated in the coming months. The design phase is anticipated to take longer due to its complexity and the need for public involvement. The goal is to utilize a runway closure in 2027 to minimize operational impacts during construction.
Budget discussions revealed a high-level cost estimate of approximately $520 million for the overall project, which includes significant design work and construction efforts. The board acknowledged the magnitude of this investment and the complexities involved, with confidence expressed in the accuracy of the estimates based on recent project data and local input.
In conclusion, the meeting underscored the importance of strategic planning and community communication as Pitkin County moves forward with its airport renovation projects. The board plans to continue discussions on funding options and construction logistics, ensuring that community concerns are addressed throughout the process.