The Public Service Commission of Maryland held a public comment hearing on March 26, 2024, regarding the controversial Pepco battery project at Livingston Road. Community members voiced significant concerns about the safety and oversight of the facility, which was planned to be located near a daycare and in a densely populated area.
One resident, who actively researched the project, highlighted alarming deficiencies in safety planning and contractor qualifications. They noted that local fire authorities had not received adequate training related to the battery installation, raising serious questions about emergency preparedness. The resident criticized Pepco for failing to engage with the community before selecting the site, which led to delays and ultimately a failed project.
The project, which represented a $6.3 million investment in the energy grid for Oxon Hill, has sparked debate over whether customers should bear the financial burden of its failure. The speaker urged the commission to prevent Pepco from recovering costs associated with the project through customer rate increases. They also called for more community engagement, recommending that the commission hold at least two public meetings to gather input from residents and ensure transparency in future utility projects.
In conclusion, the resident emphasized the need for stronger regulatory oversight of utility projects to prioritize public safety and quality of life. They advocated for common-sense regulations that protect the interests of the community and prevent similar issues from arising in the future. The commission's response to these concerns remains to be seen as they continue to deliberate on the matter.