The Greene County Regional Sewer District meeting on June 19, 2025, highlighted significant developments in wastewater management that could greatly impact local infrastructure and future growth. Project manager Tyler Hammerly from Wessler Engineering presented an analysis of potential service needs for upcoming projects, including the munitions campus and a new rest stop.
One of the key takeaways from the meeting was the projected wastewater flow from various developments. The munitions campus, which has substantial acreage, could generate up to 150,000 gallons per day, with estimates suggesting that industrial development could push this figure even higher. This potential demand underscores the need for strategic planning in wastewater management to accommodate future growth.
Another notable discussion centered around the Westcott homes development, which could add significant flow to the system if fully built out. However, the developer has recently reduced their initial request for wastewater capacity from 12,000 gallons per day to just 900 gallons, reflecting a shift in their development timeline.
The meeting also addressed the existing capacity of the wastewater treatment plant, which is rated for 50,000 gallons per day but currently averages around 12,000 to 15,000 gallons. With the plant having approximately 35,000 gallons per day of capacity available, the discussions emphasized the importance of preparing for the anticipated increases in flow from new developments.
Wessler Engineering outlined two potential routes for servicing the munitions campus, considering the topography and existing infrastructure. The proposed routes would require upgrades to the current lift station and force main systems to handle the increased flow effectively.
As Greene County continues to grow, the decisions made in this meeting will play a crucial role in ensuring that the wastewater management system can support new developments while maintaining service for existing residents. The discussions reflect a proactive approach to infrastructure planning, aiming to meet the needs of a changing community.