OCII approves 18 month extension for Mexican Museum's $38M construction project

May 21, 2024 | San Francisco City, San Francisco County, California



Black Friday Offer

Get Lifetime Access to Full Government Meeting Transcripts

$99/year $199 LIFETIME

Lifetime access to full videos, transcriptions, searches & alerts • County, city, state & federal

Full Videos
Transcripts
Unlimited Searches
Real-Time Alerts
AI Summaries
Claim Your Spot Now

Limited Spots • 30-day guarantee

This article was created by AI summarizing key points discussed. AI makes mistakes, so for full details and context, please refer to the video of the full meeting. Please report any errors so we can fix them. Report an error »

OCII approves 18 month extension for Mexican Museum's $38M construction project
The San Francisco City Commission convened on July 4, 2025, to address several key agenda items, including the approval of a formal contract with the Department of Public Works (DPW) and an amended grant agreement with the Mexican Museum.

The meeting began with a discussion on the collaboration between various city agencies, emphasizing the importance of a structured partnership with DPW to enhance parks and recreational areas in the Transbay neighborhood. As new families move into developments on Block 2, the commission expressed gratitude for the ongoing support from DPW, which has been instrumental in facilitating these improvements.

Following this, the commission moved to item 5e, which involved the Mexican Museum's request for an extension of a grant agreement. The museum, located in the former Yerba Buena Center project area, is seeking an 18-month extension to continue fundraising and implement recommendations from a recent city audit. The original grant, initiated in 2010, allocated over $10 million for the development of cultural space at 706 Mission Street. However, the museum has faced challenges in meeting financial and operational requirements, as highlighted by the audit findings.

Deputy Director Mark Slutskin presented details of the grant's history, noting that while the museum has received $6.3 million, only $4.1 million has been spent. The audit revealed issues with compliance and eligibility of expenses, prompting the museum to work closely with the city to address these concerns. The museum's leadership, including Chair Andy Kluger, acknowledged the audit's findings and expressed commitment to implementing the recommended changes.

The proposed plan includes a phased approach to construction, with an estimated total cost of $38 million for tenant improvements. The museum aims to raise $4.5 million before accessing additional grant funds, with a detailed fundraising strategy already in place. The commission discussed the importance of local business involvement in the project, emphasizing the goal of utilizing micro and small businesses during construction.

After thorough deliberation, the commission voted in favor of the motion to approve the amended grant agreement, with a tally of three ayes and two absences. The meeting concluded with a commitment to continue supporting the Mexican Museum's development and ensuring compliance with city regulations.

Overall, the meeting underscored the city's dedication to enhancing community resources and supporting cultural institutions, while also addressing the need for accountability and effective management of public funds.

View full meeting

This article is based on a recent meeting—watch the full video and explore the complete transcript for deeper insights into the discussion.