The recent government meeting in San Francisco highlighted significant developments in several infrastructure projects, focusing on traffic disruptions, cost increases, and coordination challenges.
One of the main topics discussed was the ongoing project along a 2.3-mile stretch of El Camino Real. Officials acknowledged that this project would severely disrupt traffic and require coordination with ten separate jurisdictions, making logistics particularly complex. The interrelationship with multiple system shutdowns adds to the challenges faced by the project team.
Another key issue raised was the regional groundwater storage recovery project, which is now facing a $13 million cost increase. This increase is primarily due to the need for manganese treatment facilities at nine sites. While coordination with partners such as Daly City, San Bruno, and Cal Water has been cooperative, it may lead to potential delays. However, officials reassured that the design phase is not on the critical path, meaning the overall project schedule remains unaffected.
The meeting also addressed a major variance in the habitat reserve program. A strategic shift will now require contractors to take over maintenance responsibilities for mitigation sites, ensuring the success of plantings. This change is expected to involve a $6 million increase in costs due to new oak mitigation requirements imposed by the planning department and other soft cost increases from permitting agency comments.
Lastly, an update on the Calaveras Dam project revealed a forecasted $23 million increase. This increase serves as a placeholder for improvements related to fisheries mitigation in the Alameda Creek watershed. Discussions with permitting agencies are ongoing to determine the specific improvements needed.
Overall, the meeting underscored the complexities and financial implications of these infrastructure projects, emphasizing the importance of effective coordination among various stakeholders to mitigate delays and ensure successful outcomes.