Stantec reports on South Main water project completion issues and budget savings

This article was created by AI using a video recording of the meeting. It summarizes the key points discussed, but for full details and context, please refer to the video of the full meeting. Link to Full Meeting

Wolfeboro's South Main Water Main Replacement Project is nearing completion, with significant progress reported during the Select Board meeting on July 16, 2025. Jonathan from Stantec, the engineering firm overseeing the project, presented an update highlighting that the project is approximately 99% complete, with only minor issues remaining to be resolved.

The project, which faced delays due to unforeseen infrastructure and challenging weather conditions, was initially scheduled for completion on June 6 but was extended to June 18. The total working days increased from 160 to 172, reflecting a 10% rise in allowable work time. Jonathan noted that the wet spring and hot June hampered turf establishment, prompting a $5,000 holdback from the contractor, Dawson's, until the turf is adequately established.

Financially, the project is approximately $450,000 under budget, with total construction costs around $2 million. This savings stemmed from efficient management of resources, including a reduction in necessary dewatering days and fewer lead service line replacements than anticipated. The project was funded through a combination of federal and local contributions, with the federal share covering about 60% of the costs.

Community feedback highlighted concerns about night work, particularly from local businesses and residents near the Brewster properties and Pickering House. Jonathan acknowledged these complaints and explained that night work was strategically chosen to minimize daytime traffic disruptions. He also addressed issues regarding the aesthetics of granite curbing and the challenges of maintaining traffic flow during construction.

Looking ahead, the Select Board is considering implementing mandatory night work for future projects to further reduce daytime disruptions. Additionally, improved communication strategies with the public are being explored to enhance transparency and keep residents informed about ongoing and upcoming projects.

Overall, the meeting underscored the importance of infrastructure improvements in Wolfeboro while balancing community needs and expectations. The Select Board and Stantec are committed to addressing remaining issues and ensuring the project concludes successfully, paving the way for future developments in the town.

Converted from 16 July 2025 Wolfeboro Select Board Meeting meeting on July 18, 2025
Link to Full Meeting

Comments

    View full meeting

    This article is based on a recent meeting—watch the full video and explore the complete transcript for deeper insights into the discussion.

    View full meeting

    Sponsors

    Proudly supported by sponsors who keep New Hampshire articles free in 2025

    Scribe from Workplace AI
    Scribe from Workplace AI