The Braintree Planning Board convened on August 6, 2025, to discuss the development plans for a new residential project along the riverfront. The meeting focused on the design and construction phases of the project, which aims to integrate the natural landscape into the living environment for future residents.
The presentation began with an overview of the Phase I buildings, which are designed to enhance views of the river and promote pedestrian access. The buildings will range from 67 to 108 units, all standing four stories tall, with unique designs tailored to their specific locations on the site. The layout includes multiple access points and a paved sidewalk system to encourage walking and interaction with the surrounding landscape.
Key features of the development include a primary amenity space located in Building 1A, which will serve several buildings, as well as smaller amenity areas in Buildings 4 and 5. These spaces will offer residents lounge areas, co-working spaces, and fitness facilities. The design emphasizes a cohesive aesthetic while ensuring each building maintains its distinct identity through varied colors and architectural details.
Nick Delacaba, a professional engineer with Allen and Major Associates, provided insights into the civil aspects of the project. He outlined the phasing plan, indicating that Phase I will encompass Lots 1 and 3, totaling 427 units, while Phase II will include Lot 2 with an additional 325 units. The project adheres to zoning requirements, with a parking plan that exceeds the minimum space requirements, including provisions for electric vehicle charging stations.
The meeting also addressed fire access and circulation, highlighting the design of driveways and a bridge crossing to ensure emergency services can reach both sides of the river. The planning team is coordinating with the MBTA for access approvals and has proposed designated areas for snow storage to manage winter conditions effectively.
Overall, the Braintree Planning Board's discussions underscored a commitment to creating a sustainable and accessible residential community that harmonizes with the natural environment. The next steps involve finalizing approvals and continuing collaboration with local authorities to ensure the project's successful implementation.