During the recent City Council Workshop held on September 17, 2025, in Haslet, Texas, officials discussed significant infrastructure projects aimed at improving local services and traffic flow. One of the primary topics was the reconstruction of Maxwell Circle, a project that is being undertaken in collaboration with Tarrant County.
The discussion highlighted the necessity of this project, particularly in relation to the expansion of the local fire station. City officials noted that the fire department required reliable sewer services to meet its operational needs. Historically, providing sewer access along the 156 corridor has posed challenges. However, a thorough analysis revealed that extending sewer lines from Buffalo Creek through Maxwell Estates would not only serve the fire station but also benefit a larger drainage area.
The proposed sewer line will be installed at depths ranging from 15 to 19 feet, which raised concerns about potential impacts on the existing roadway. To mitigate these concerns, the county granted a right-of-way construction permit with the stipulation that the city would assist in rebuilding Maxwell Circle after the sewer installation is completed. This agreement underscores the collaborative effort between the city and county to ensure that infrastructure improvements do not compromise road integrity.
Additionally, the meeting touched on traffic management strategies, particularly the dedicated right-hand turn lane off Westport Parkway, designed to facilitate smoother traffic flow towards Kellerhasset Road. This improvement aims to enhance connectivity and reduce congestion in the area.
In conclusion, the discussions during the workshop reflect a proactive approach by the City Council to address infrastructure needs while ensuring that essential services, such as those provided by the fire department, are adequately supported. As these projects move forward, the community can expect improved traffic conditions and enhanced public safety services.