The Kootenai County Board of County Commissioners meeting on September 30, 2025, provided updates on several ongoing construction projects, including HVAC system replacements and the Veil Pod project.
The meeting highlighted the upcoming shutdown of the HVAC system in a county building, scheduled to begin on October 6. This shutdown will last approximately two weeks as the old system is removed and a new one is installed. Staff will receive notifications about the temporary lack of HVAC, with recommendations to use space heaters or fans to manage comfort levels during this period.
Additionally, the board discussed the JL HVAC project, which has encountered a higher-than-expected bid from the contractor, Apollo. However, officials are exploring alternative equipment options that could save around $100,000. A final cost estimate is expected within the next two weeks as engineering designs are finalized.
The meeting also addressed progress on exterior concrete work, specifically the ADA walkway, which is nearing completion. The concrete pour is scheduled for tomorrow, with minor adjustments to railings anticipated in the following weeks.
Lastly, updates on the Veil Pod project revealed significant progress, including the completion of the rec yard block and the assembly of holding cells on the second level. Minor change orders have occurred, including a $3,000 adjustment for additional shower components and roof penetrations for mechanical venting. Overall, the project remains on track with healthy contingencies.
The meeting concluded without further questions, indicating a smooth progression of these essential county projects.