The Surtax Oversight Committee Meeting held on October 7, 2025, in Bay County, Florida, focused on the progress of various infrastructure projects funded by the local surtax. The meeting began with an update on the completion of projects from the first five years of the surtax program, with the exception of Magnolia Beach Road Phase 2. This project has recently been approved for construction by the board, marking a significant milestone in fulfilling the surtax commitments.
The delay in the Magnolia Beach Road project was attributed to grant funding complexities, particularly involving collaboration with the Navy. The committee noted that the rising costs of construction, especially for sidewalks, have posed challenges, with current prices exceeding $200 per linear foot.
Looking ahead, the committee reported that all projects planned for the next five years are either completed in design or currently under construction, with only one exception: County Road 388 at US 231. This update reflects the committee's ongoing efforts to manage and execute infrastructure improvements effectively.
In conclusion, the meeting highlighted the successful completion of initial surtax projects and outlined the progress of future initiatives, emphasizing the importance of addressing funding challenges and rising construction costs. The committee remains committed to ensuring the timely execution of remaining projects.