Perry County approved Frederick Sheet Metal to replace failed HVAC equipment at the River’s Edge animal shelter and tabled replacement of an in‑building HVAC unit at the South Annex until staff verifies contracts and appropriations.

Commissioners approved a Frederick Sheet Metal bid to replace failed HVAC equipment at the River's Edge animal shelter, citing unit age and damage from the shelter environment. Commissioners also agreed to table a separate HVAC replacement at the South Annex until staff gathers contract details and appropriation balances.

Molly, who oversees building maintenance for the shelter, said three air handlers at the shelter—likely original equipment from roughly 20 years ago—have begun failing and that the environment (animal odors and moisture) accelerates wear. She said one unit already failed and a second was showing signs of imminent failure. "All 3 of these units are reaching end of life," she said.

Frederick Sheet Metal provided a bid; commissioners approved the lower bid at the meeting. "I make a motion to approve the Frederick's," a commissioner said; the motion passed on a voice vote.

Separately, the South Annex has an interior gas furnace unit with high CO2 readings reported by the service contractor. Building maintenance presented two replacement options (replace inside unit only or replace the entire system with a higher‑efficiency 97% gas unit). The commissioners asked staff to confirm whether there is an active maintenance contract with Frederick and to check the South Annex maintenance appropriation before proceeding. A request to table the South Annex HVAC replacement until staff can collect contract and budget information was made and the board voted to table that item for two weeks.

Why this matters: The shelter HVAC replacements address immediate equipment failures that affect animal care and staff safety. The South Annex decision was deferred to avoid acting without confirmed contract and appropriation information.

What happens next: The county will pay Frederick Sheet Metal for the animal shelter work after invoice processing; for the South Annex, staff will review the existing maintenance contract and remaining appropriation and return to the commissioners at the next meeting with the information requested.