Public works staff asked the council to approve a task order of $61,900 to engage Mark Russo Associates for construction engineering and inspection (CEI) services on the Wellington Tennis Center expansion.
Staff said the village’s engineering team could not absorb all on-site CEI requirements for electrical installations and certain vault work during construction. The contracted CEI firm would attend the site three times a week, participate in weekly contractor meetings and provide final certifications that installation met contract specifications.
Why it matters: CEI services provide construction oversight and a certified record that work was completed per contract; staff said the funding is already allocated in the project’s capital budget and that the task order would not delay the project.
Staff noted the CEI firm is the original design engineer for the tennis center and that the additional services respond to construction-phase needs. The task order was presented for council approval; the transcript records the staff explanation and confirmation that the $61,900 is in the capital budget but does not record a final vote.