City details $20M operations center master plan; phase 1 estimated about $10M
Summary
Public Works presented a 20‑year master plan for the operations center, including expanded admin and maintenance buildings, fleet maintenance and potential future fuel station; phase 1 design funds are in the 2025 budget.
Get email alerts on the Capital Projects topic
No spam. Unsubscribe anytime.
Public Works staff presented a master plan for the city operations center to the council on Aug. 18 that identifies facility needs to support the city’s expected 20‑year growth and operations. The architect estimated a full buildout cost above $20 million and recommended a phase‑1 package of roughly $10 million that would focus on warehouse/shops and an administration addition.
Public Works staff outlined a site concept that preserves a wetland area while concentrating new shop, storage and mechanic facilities in the rear of the site and an admin/training expansion in the front. The long‑range plan envisions a new fleet maintenance building with a wash bay, evidence storage, covered parking, shop warehouses and a possible fueling station location reserved for the future.
Staff said the architect is completing a final report and that the city already has design funds in the 2025 budget for next steps. Staff described procurement alternatives that could accelerate delivery and potentially lower risk, including design‑build and general‑contractor construction manager (GCCM) approaches; both require state approvals.
Quotes: “The master planning process allows the city to make good and efficient and cost effective decisions,” the presenter said. The architect’s overall estimate for full‑site improvements was “20 plus million,” with a phase‑1 anticipated at about $10 million.
Next steps: Architect finishing the report; staff will evaluate procurement methods, confirm phase‑1 scope and schedule design and construction funding.