Clean Water Services flags wet‑weather rules, 1200‑C permit updates and average review timelines
Summary
Clean Water Services reported average site‑development and environmental review turnaround of 12–15 business days, described new wet‑weather corrosion control requirements and urged developers to review the draft 1200‑C construction stormwater permit.
Clean Water Services (CWS) told development professionals that its typical site‑development and environmental reviews currently average 12–15 business days and that contractors and developers should prepare for stricter wet‑weather erosion‑control requirements and a renewed state 1200‑C construction stormwater permit.
Damon Reiche, planning and development services division manager with Clean Water Services, said “both our site development reviews and our environmental reviews for service provider letters are between 12 and 15 business…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat