Highway staff outline summer paving, bridge work and culvert replacement
Summary
DeKalb County highway staff reported on planned community crossing paving in July, scheduled culvert delivery, Bridge 17 deck removal progress and that Auburn will not join sidewalk widening on Bridge 503; roadside mowing and dust-control plans were also discussed.
Get email alerts on the Transportation Infrastructure topic
No spam. Unsubscribe anytime.
DeKalb County highway staff briefed the commissioners May 27 on a suite of summer road and bridge projects, including planned paving, culvert replacement and ongoing bridge work.
Staff said API is scheduled to begin community-crossings paving in July on County Roads 35, 60 and 72 and that paving on portions of Auburn Drive is tentatively scheduled for the same period. Dust-control crews are tentatively scheduled for June. The highway department has begun roadside mowing and is placing pipes on Berman and Kitchen roads.
Culvert replacement: Staff said a culvert for County Road 35 (south of County Road 12) will be delivered the day after the meeting and crews expect to begin installation the following week.
Bridge work: Bridge 17 (on County Road 79) is undergoing deck removal; staff described using a mini excavator with a hammer to remove the deck and noted the process is time-consuming, with crews removing the existing deck and preparing the structure for replacement. Staff said the existing deck had significant deterioration.
Sidewalk decision on Bridge 503: Staff reported Auburn will not participate in a sidewalk or widening project on Bridge 503 (Auburn Drive), and the county plans to proceed with bridge repairs without widening or adding a sidewalk. Staff said Auburn officials felt there was not sufficient connectivity demand in that area to justify participation.
Why it matters: The projects involve county-maintained roads and bridges where closures and construction will affect travel and local access; culvert and bridge work addresses safety and infrastructure condition.
Next steps: Staff will proceed with scheduled deliveries, coordinate with API for paving in July, begin dust-control work in June if schedules hold, and continue bridge-deck removal and replacement work. Commissioners asked staff to monitor schedules and report any changes.