TBC Phase 2 update: cabinet millwork, internet and generator work progressing; move-in date to be finalized

5923338 · February 17, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff updated the Farmers Branch Senior Advisory Board on TBC Phase 2 renovations: cabinet millwork is being installed, internet and AV work are next, and a backup generator is expected to be installed pending permit inspections; staff are meeting contractors to confirm a firm move-in schedule.

A staff member updating the Farmers Branch Senior Advisory Board said work on TBC Phase 2 is progressing and that cabinet millwork is being installed in offices, internet service is being brought online and audio-visual work will follow.

The update matters because the Branch Connections programs and the Senior Advisory Board depend on the facility’s reopening to resume regular operations. Staff said progress on utilities and the backup generator are key steps before move-in.

Staff described the current status: cabinet millwork is in place in offices; internet connectivity is being established to support AV installation; ballroom chairs have been received and are stored; and a backup generator pad is complete and awaiting a permit and inspection. “In theory, the backup generator should be complete before the end of this month,” the staff member said. After the generator inspection, staff said bringing power to the building is expected to take less than three days to connect.

Staff cautioned that the generator and utility work are components of the project and that the installation of the generator does not by itself constitute final move-in. Staff said they are meeting with contractors to firm up a definitive move-in date and promised to notify board members and to begin marketing and communication about the reopening once that date is set.

Board members asked about specific finishes such as ballroom floors and wall panels; staff said overhead lighting work is underway and that the floor will be redone toward the end of the renovation schedule. No formal action was taken; staff will provide an update to the board when a move-in date is confirmed.