Board approves change order packet for Hopewell East, adds $91,489.78 and six days to contract
Summary
The Board approved 13 change orders for the Hopewell East project, increasing the Milestone Contractors contract to about $14.01 million and adding six days for completion; staff clarified the contract completion date remains Dec. 2, 2024.
The Board of Public Works on Aug. 12 approved change order packet No. 5 for the Hopewell East project, adding $91,489.78 to the contract and six calendar days to the schedule.
Roy from the city engineering department told the board the project was awarded to Milestone Contractors in June 2023 for $13,373,284.9 and that prior change orders totaled…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat