Wastewater pump-enclosure project far behind schedule; SRF loan and scope changes cited
Summary
Council asked staff for a funding history after hearing that the SRF-funded pump-enclosure project has been extended more than 570 days, has required reengineering and change orders, and now shows a larger carry-forward in the 2024–25 CIP.
City of Cape Canaveral staff told the council Aug. 12 that a multi-year wastewater pump-enclosure project (CIP WW17) funded in part by a State Revolving Fund (SRF) loan has experienced major delays and scope changes that have pushed cost carryovers into the 2024–25 budget.
At the workshop Public Works staff and Tim (project staff) said the construction agreement was signed in 2022, then engineers discovered underground utility conflicts and other issues that required redesign and resulted in multiple change orders.
Why it matters: The delay has increased the project timeline and changed how the SRF…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat