Board approves $3,686 change order for Longview Greenway repair
Summary
The Board of Public Works approved change order No. 1 for the Longview Greenway project to correct a drainage issue at the Eastern Drive approach, increasing the contract by $3,686.28 and adding three calendar days to the schedule.
Get email alerts on the Greenway Maintenance topic
No spam. Unsubscribe anytime.
The Bloomington City Board of Public Works on July 29 approved change order No. 1 for the Longview Greenway project to correct a drainage problem at the Eastern Drive approach.
Jason Kerwin of the engineering department explained that an installed approach at 3200 Longview was found to hold water after a rain event. The contractor will remove a portion of the approach and add curb and gutter with an angle to direct water into an existing drain. Kerwin said, "The original contract price was $549,433.45. The additional charge, through the contractor is $3,686.28, bringing the new contract to $553,119.73." He added the change order adds three calendar days to the contractor’s schedule.
The board approved the change order on a roll call vote recorded as Carone Aye, Roach Aye and Cox Deckard Aye. No public comment was recorded on the item at the meeting.