Otsego council approves $30,456 in change orders for drinking-water project and grants 7-day extension
Summary
Council approved four change-order items for the Lehigh House 4 drinking water improvement project — primarily a missed grout/sloping detail in a backwash tank — adding $30,456.76 to the contract and a seven-day extension to completion dates.
The City of Otsego council on July 28 approved change orders totaling $30,456.76 to contractor Markett and Johnson for the Lehi House 4 drinking water improvement project and granted a seven-day extension to the project’s substantial and final completion dates.
AE2S project staff told the council the largest item — change order No. 9, roughly $41,000 in the project materials — addressed missing grout and floor slope work in a backwash tank that was omitted from bid…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat