Otsego council approves $30,456 in change orders for drinking-water project and grants 7-day extension

5923088 · July 29, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Council approved four change-order items for the Lehigh House 4 drinking water improvement project — primarily a missed grout/sloping detail in a backwash tank — adding $30,456.76 to the contract and a seven-day extension to completion dates.

The City of Otsego council on July 28 approved change orders totaling $30,456.76 to contractor Markett and Johnson for the Lehi House 4 drinking water improvement project and granted a seven-day extension to the project’s substantial and final completion dates.

AE2S project staff told the council the largest item — change order No. 9, roughly $41,000 in the project materials — addressed missing grout and floor slope work in a backwash tank that was omitted from bid…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans