Committee defers vote on $182,709 Schofield Avenue amendment, asks for design/construction breakdown and schedule
Summary
Committee members debated a $182,709.38 change order for Schofield Avenue construction services, questioned why the amendment combined design and construction costs, and voted to defer approval until contractors supply a clear cost breakdown and construction schedule.
The Public Works and Utility Committee debated a proposed $182,709.38 amendment to the Schofield Avenue construction services contract and voted Aug. 11 to defer action until staff provides a clearer separation of design and construction costs and a schedule showing how the amendment affects project completion.
Staff said the amendment covers both additional design work and time-and-materials construction observation tied to a longer-than-anticipated construction duration. Public works staff and the design consultant said the project evolved from an anticipated pavement replacement to a larger…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat