High school renovation moves into steel and interior finish work; district eyeing December turnover

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Construction manager reported progress on structural steel, MEP, terrazzo and low-voltage work at the Pleasant Valley High School renovation and said the district should see the next phase turned over in December.

Mike, the construction project representative for CHA, gave the board a monthly update on the Pleasant Valley High School renovation, reporting work on interior mechanical, electrical and plumbing systems and exterior structural steel.

The superintendent, Dr. Conrad, and board members asked schedule and sequencing questions as the contractor detailed completed foundation and footing work, placement of structural steel for the administration addition, new terrazzo in cafeteria-area bathrooms, and continuing low-voltage and head-end equipment installation. Mike said the team is “on…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans