Committee reviews CIP and street projects; Oakley River Bridge repairs and storm-pond work highlighted

5930021 · July 15, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

Committee received a Capital Improvement Plan update covering road and utility projects, including ongoing work on Watson Avenue, Schofield Avenue reconstruction, a large storm pond at Kelly Land Park, and an Oakley River Bridge repair estimated near $9,500.

Committee members received a multi-topic capital improvement and construction update on July 14 that summarized ongoing street and utility projects and near-term priorities.

Staff reported several active projects: the Watson Avenue water main work is continuing with pipe crews returning this week; crews encountered an irregular topsoil/organic layer in places that requires excavation and replacement with suitable base materials. A previously mentioned multi-use path along Alderson to Birch was paved two weeks ago, and contractors are completing side-slope restoration and punch-list items on other resurfacing projects (East Jellick, Von Kennel, Fuller Street and Schofield Avenue phases).

The committee was briefed on several larger-site activities. A storm pond at Kelly Land Park is being excavated; sand from that site is being stockpiled at the Ryan Street material site for future use. Staff said the Cedar Creek interceptor road project is in the easement-exhibit and scope-evaluation stage with consultant MSA. The Well 4 GAC tanks were also discussed in the utility update (see water article) and Well 3 was submitted for an emerging-contaminant safe-drinking-water loan in June.

Staff reported a small contract repair to the Oakley River Bridge performed by Norcon Company; the contractor completed work in two days at a cost of about $9,500. Committee members raised long-term concerns about the bridge's structural life and discussed coordination with county plans (Highway J) to avoid simultaneous closures that would significantly reroute traffic.

Other construction notes included: retaining-wall work at a corner tied to a separate project (utilities too close to edge), a two-foot deep excavation and base replacement on Bushka Street, culvert installation on Shorey between Anastasia and Heron ahead of pulverize-and-overlay work, and multiple pavement and driveway restorations where recent water-main repairs occurred (Alderson, Volkman). Staff said that recent small-scale, surprise repairs to water mains have highlighted the need to keep a pipeline-replacement schedule.

On system-wide planning, staff reiterated the utility master-plan priorities: building a consolidated treatment facility to treat water from Wells 1 and 5 (design and construction staged after Well 3 work, with a conceptual construction start targeted around 2028), and a 2029 project to replace water and sewer under Business 51. Staff said the village still has approximately 9 miles of asbestos-cement main and about 7 miles of older cast pipe (about 16 miles of aging pipe total) and discussed an objective of replacing roughly 1.5 miles of water main per year to manage asset life-cycle risk.

Staff also described grant funding contexts. The committee discussed STP (Surface Transportation Program) urban projects: roads must be on the MPO urban-classified system to qualify; if pursued, the program typically funds around 80% of eligible costs with a 20% local match. Staff recommended considering sections of Schofield Avenue and Birch Street as candidates for upcoming grant rounds.

No formal committee action was required on the CIP update; staff asked trustees to review the materials and provide feedback in the coming weeks.