Get Full Government Meeting Transcripts, Videos, & Alerts Forever!
Castleberry ISD bond update: new high school 30% complete, storm-shelter work a major cost driver
Summary
Bond program manager said the 2024 high school bond construction is about 30% complete by time and about 25% of budget spent; the storm shelter accounts for a large share of new-construction cost and site work and waterline work are next steps.
Cameron Holloman, Castleberry ISD bond program manager, told the board the 2024 high school bond project is on schedule and that the program is roughly 30% complete in construction time and about 25% expended financially.
Holloman said underground and decking work are largely finished, with many pours completed and roof decking mostly in place. He said the district expects to be enclosed by January–February and anticipates moving into parts of the campus (media center and related areas)…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat

