Castleberry bond update: steel up and major site work underway at new high school; band hall due Oct. 1
Summary
Bond program manager reported progress on the 2024 high school bond: steel erection and slab on grade nearly complete, band hall renovation around 60% complete with October turnover, parking and stormwater work ongoing and some schedule risk tied to utility coordination and city approvals.
Bond program manager Cameron Holloman told the board that construction on the 2024 high school bond remains on schedule overall despite rainy weather and coordination challenges with utilities.
"We are wrecking steel," Holloman said, and reported slab-on-grade work largely complete and steel erection underway; he estimated foundations and steel will be complete by September and that the project should be dried in by January–February to begin interior work.
Holloman reviewed several active elements: permanent power has been switched on, underground storm-water work is…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat