Casper High School bond work on schedule and within budget, district reports
Summary
Bond program manager reported the high school addition and renovations are roughly 30% complete, the city will reimburse architects and engineers for waterline design costs, and the project’s next milestone is a topping-out ceremony in late March 2026.
Mister Holloman, providing the Castleberry High School bond construction update, told the board the project is on schedule and within budget and that several milestones are approaching.
Holloman said the project is roughly 30% complete and that the district has paid out about 29% of the guaranteed maximum price (GMP). He announced the project’s “top-out” — the placement of the highest structural element — will take place on a Wednesday at about 1 p.m. (date provided to board) and that board members…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat