Harford County held a public hearing on Oct. 7 to consider updates to the Water and Sewer Master Plan (Resolution 014-25). Don Becker, identified in the meeting as Water and Sewer staff, summarized proposed workbook edits that remove completed developments, adjust residential equivalent unit counts and revise capital project timing.
Key points from the staff presentation
- Project removals and unit adjustments: Staff proposed removing Trimble Meadows and Van Bibber from the proposed-developments list because those projects are complete. Staff also said Grace Hall added 63 residential units that moved into the Water & Sewer 1 category.
- Tables and timing updates: Table 3‑1 (proposed developments) and Table 3‑8 (planned waterworks immediate, 5‑year and 10‑year priority) were revised to reflect recent changes. Staff said Table 3‑8 was updated to add one Harford County project and to adjust the timing schedule for several other projects.
- Municipal requests: The City of Aberdeen and the City of Havre de Grace requested updates to capital-project listings; staff said the workbook table includes only projects with proposed changes and that a comprehensive list appears in the full Water and Sewer Master Plan document.
Public process and outcome
- No public speakers: The chair announced there were no signups for the public hearing and the hearing on Resolution 014‑25 was concluded at the meeting.
Ending: Staff indicated the workbook presents only proposed changes and directed members to the comprehensive master-plan document for full listings and schedules.