Commission accepts Atlantic Development bid to start Phase 1 stormwater repairs at Basin 1
Summary
After reviewing three bids, the commission voted 5-0 to accept Atlantic Development's proposal for Phase 1 of Basin 1 stormwater improvements and to move forward with scoping and grant outreach.
Get email alerts on the Stormwater topic
No spam. Unsubscribe anytime.
The Melbourne Beach Commission voted 5-0 to accept Atlantic Development of Cocoa Inc.’s proposal to begin Phase 1 of Basin 1 stormwater improvements, following staff and engineer briefings on competing bids and alternatives.
Nut graf: The vote sends the town into contracting and grant-seeking steps for a basin where residents have reported repeated flooding; engineers will perform camera scoping and produce specifications to support an RFP for construction.
Body: Town staff distributed three bids for Basin 1 repairs. The board heard that Atlantic Development’s Phase 1 number was competitive against JobAir (sometimes listed as Joe Baer/Jobair in documents) and Brewer Paving. Commissioners and staff discussed a set of alternate scopes: full 36-inch pipe replacement across the length of the line, targeted replacements across Riverside Drive, replacement across green space, or sleeving the existing pipe. Bids included different prices for camera scoping — Atlantic quoted $25,000, Brewer roughly $26,006, and another bidder about $62,010 — and commissioners emphasized that scoping the pipe was the next priority.
Town Manager Elizabeth Mascaro told the commission that having bid documents and engineering packages would also support pursuing state and federal grants; commissioners asked staff to contact grant assistance organizations that the town belongs to. Commissioners and several residents described recent incidents of flooding in the Cherry-and-Cedar street area and asked that the selected contractor coordinate closely with engineers to confirm actual pipe conditions before major construction.
The vote: After discussion, the commission accepted Atlantic Development’s Phase 1 proposal and directed staff to move forward with contract negotiations and grant pursuit. Staff noted that the scoping work should be done first to refine final construction scope and cost estimates.
Ending: With the award to Atlantic Development, the town will commission camera scoping and engineering specifications and then issue construction RFP(s). Commissioners said they expected follow-up reports on grant prospects and bid results before construction starts.