Town Administrator Andrew told the Select Board the fire substation concrete slab is being poured, exterior framing will begin, new 4-way stops are in effect and materials for the Oct. 20 special town meeting are posted online.

Town Administrator Andrew updated the Select Board Tuesday on construction at the new fire substation, recently implemented traffic-pattern changes and materials for a special town meeting scheduled Oct. 20.

On the substation, Andrew said the concrete slab for the apparatus bay is being poured and exterior framing is scheduled to begin this week, with framing expected to be completed before the end of the month. “Be sure to check out the progress when you attend town meeting next week,” Andrew said and directed residents to the town website for more information.

Andrew also reminded residents that two intersections have been converted to four-way stops—Stafford Street at Center Depot Road and Center Depot Road at City Depot Road/H K Davis Road—and asked drivers to take care navigating the new patterns. He noted the special town meeting materials are available online at townofcharlton.net/stm20five and encouraged residents to review the warrant prior to the Oct. 20 pre-town meeting and special town meeting at Charlton Middle School.

Andrew said he would be at the senior center the next morning to meet residents and answer questions about town business.