New Hoke County high school nears occupancy; contractor work at 61% pay, contingencies remain

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

District and contractors reported the new high school is roughly 84% complete on the schedule, with pay at about 61% and approximately $636,000 remaining in contingencies; occupancy and demolition of old buildings are expected next summer following move-in, with some schedule risk from wet weather.

District staff and the construction team told the Hoke County Schools board on Oct. 14 that the new high school is taking final interior and exterior finishes and is on track for occupancy in the coming spring, with final site demolition to follow.

The presenter said exterior brickwork is complete, the main entry and parent drop-off loop are visible, glazing systems are being installed, and interior work including drywall, painting and mechanical finishes is progressing. The gymnasium, cafeteria, commons and science labs were shown as…

Already have an account? Log in

Subscribe to keep reading

Unlock the rest of this article — and every article on Citizen Portal.

  • Unlimited articles
  • AI-powered breakdowns of topics, speakers, decisions, and budgets
  • Instant alerts when your location has a new meeting
  • Follow topics and more locations
  • 1,000 AI Insights / month, plus AI Chat
30-day money-back on paid plans