Bids for Central Park and Guadalupe Transit Hub come in under budget; staff to tabulate and confirm award

AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

City staff reported multiple bids for the Central Park renovation and Guadalupe Transit Hub projects that came in below or near budget. The Central Park engineer's estimate was $3.8 million and the bid low was about $3.406 million; the transit hub low bid was $1.617 million against a $1.6 million budget.

City staff told the Guadalupe City Council Oct. 14 that bids for two capital projects ' the Central Park renovation and the Guadalupe Transit Hub ' arrived within or close to the budgeted amounts and will be tabulated for next steps.

During his report, staff provided the following bid results for the Central Park renovation (base bids): Quinn Quincun Inc., $3,420,000; Guyani Companies, $3,547,000; Lopez Junior's Inc., $3,527,000; SW Construction, $3,406,000. Staff said the engineer's estimate for Central Park had been $3,800,000 and the total available budget for the project was $4,700,000, which includes design and construction management.

For the Guadalupe Transit Hub project staff reported two bids: JF Will Company Inc., $1,617,000, and Taylor Jane Construction, $1,827,000. Staff said the project budgeted amount was $1,600,000 and that award might require a small transfer of funds; staff indicated available AHSC grant funds could be reallocated to cover a shortfall.

Why it matters: Staff said bids coming in at or under estimates give the city flexibility to manage contingencies and consider alternates. The council received the bid figures and asked staff to finalize tabulation and funding sources before returning with a recommendation on award.

Next steps: Staff will finalize bid tabulation and confirm budget availability, noting the Central Park project bids were described as "within budget" and the transit hub bids as "very close to budget." The council did not take an award action at the Oct. 14 meeting.

Ending: Staff said they will return with a formal recommendation on contractor award after confirming tabulation and funding allocations.