Redevelopment commission approves a series of capital change orders, sculpture relocation and design contract

5936315 · October 8, 2025
AI-Generated Content: All content on this page was generated by AI to highlight key points from the meeting. For complete details and context, we recommend watching the full video. so we can fix them.

Summary

The Greenwood Redevelopment Commission approved multiple change orders and small contracts at its meeting, authorizing TIF funds and other project expenditures and awarding a design contract not to exceed $575,200 for a Main Street corridor project.

The Greenwood Redevelopment Commission at its regular meeting (convened at 4:30 p.m.) approved several capital project change orders and small contracts, authorized a $64,435.68 TIF payment for a roadway project, and approved a not‑to‑exceed $575,200 professional services agreement for design and inspection of a Main Street corridor segment.

The commission approved a requested Southwest TIF allocation of $64,435.68 to cover remaining change orders on a road project described in the capital report. Commissioners voted 5–0 to authorize the payment.

Commissioners also approved a $2,260 contract to repaint a public sculpture planned for the Abert Roundabout and a separate $2,000 contract to move and place the same sculpture on its new pad. Staff said the artist recommended repainting the work after it is moved so the finish better matches its original color. Both small contracts were approved by unanimous roll call votes.

Other construction items approved included SCS Construction change order No. 59 for $6,332.15 to address final cleanup and landscaping along the trail near the pond and sports fields, and a $62,234 change order to install enhanced irrigation around the splash pad and playground area in a southeast park. Both were approved 5–0.

During the capital projects discussion, staff presented a professional services agreement for design and inspection of the next Main Street corridor segment (Meridian to Polk). The commission approved a not‑to‑exceed amount of $575,200 for the contract; staff said most construction work is expected in 2026 and that the contract is an hourly, not‑to‑exceed arrangement intended to cover design, inspection and associated services.

The chair and multiple commissioners emphasized that certain utility relocations would occur at the utility owners’ expense and that construction spending is planned for 2026. Staff repeatedly characterized the $575,200 figure as a not‑to‑exceed amount with some built‑in cushion to cover 2026 price levels.

Votes at a glance

- Approval of minutes from Sept. 9, 2025 — Motion approved (5–0). - Southwest TIF payment for road change orders, $64,435.68 — Approved (5–0). - Abert Roundabout sculpture repaint contract, $2,260 — Approved (5–0). - Contractor (Nasby/contractor) to move sculpture, $2,000 — Approved (5–0). - SCS Construction change order No. 59, $6,332.15 — Approved (5–0). - Enhanced irrigation change order, $62,234 — Approved (5–0). - Professional services contract (Main Street corridor design/inspection), not to exceed $575,200 — Approved (5–0).

No votes failed or were tabled during the capital projects portion of the agenda. Commissioners used TIF and one‑time infrastructure funds (including previously allocated ARPA dollars, as noted by staff) to pay for the listed items.

Ending

Commission members closed the capital projects segment after approving the listed change orders and contracts and moved on to the financial report portion of the agenda.