Council accepts completed Sherwood Hall interior rebuild after extended delays, change orders
Summary
The council accepted the completed interior rebuild of Sherwood Hall (city building) after a long sequence of change orders and unforeseen structural repairs. Staff described the work as evolving from a minor roof repair to a full interior build‑back.
Get email alerts on the Capital Projects And Procurement topic
No spam. Unsubscribe anytime.
The Salinas City Council accepted final completion of a lengthy Sherwood Hall repair and interior build‑back project during the Oct. 14 meeting, after staff described a series of unanticipated structural problems that expanded the scope and schedule.
Public Works explained that the work began as a planned roof repair intended to waterproof an existing roof membrane. During the subsequent interior abatement and build‑back phase, contractors uncovered widespread deterioration in the roof deck and supporting elements. Staff said removal of a metal deck revealed that HVAC systems and some interior walls relied on the deck for support; the discovery required removal and replacement of structural components, additional abatement, ADA restroom reconfigurations and other corrective work that considerably increased schedule and cost.
Why this matters: The project moved from a limited repair to a near‑complete interior rebuild. Councilmembers said the conversion produced many change orders; staff reported roughly 20 change orders and that the original contractor, Premier Builders, responded to emergent conditions after initial solicitations produced no local bids.
Council questions and answers: Councilmembers asked why no local contractors bid on the work and why the scope expansion was not foreseen. Staff said initial bids returned no respondents; the city solicited contractors who had previously worked for the city and Premier Builders was the responding firm. Staff also said the building’s condition produced cascading repairs (including a discovered sewer leak and non‑compliant wall construction) that were not visible without opening walls and removing the deck.
Financial and oversight details: The council discussed a sizable cost increase (one councilmember estimated a 92% rise compared with initial estimates) and emphasized lessons learned for future procurement and scope definition. Staff said the project remained under public‑works oversight and that abatement, structural repairs and ADA upgrades were necessary to meet building and safety standards.
Ending: The acceptance was approved as part of the consent agenda. Councilmembers asked staff to document lessons learned, improve upfront scope investigations for older buildings, and communicate procurement challenges and local contractor outreach in future reports.