Board approves phased Wethers Creek High School plan aligned to $130 million county funding
Summary
The board accepted a scaled project scope for the new Wethers Creek High School designed to fit a $130 million budget; administrators said the plan is tight and will require careful cost controls and contingency use.
Get email alerts on the School Construction topic
No spam. Unsubscribe anytime.
The Iredell‑Statesville Schools Board of Education approved a revised, phased scope for Wethers Creek High School that aligns construction and site work with an available $130,000,000 funding envelope the county provided.
Scott (construction staff) and the district’s architects explained the revised scope — described in the meeting as “phase 1a” — and presented a cost breakdown that showed roughly $114,000,000 estimated construction costs, about $3.4 million for a 3% contingency, and additional allowances for design fees and inspections. The board was told the plan is “tight” and will require close oversight.
Chairman Howell asked about risk. Construction staff said contingency funds are included and suggested additional strategies — including e‑rate purchases for some technology and tax rebate opportunities — to manage potential shortfalls.
Why it matters: Wethers Creek is a high‑cost capital project that will shape the district’s footprint and capacity planning. The board and administrators emphasized the desire to get shovels in the ground while staying within the county’s appropriation.
Board reaction and vote: After discussion, a motion to accept the revised scope and proceed was made and recorded in the transcript as passing by a 7–0 voice vote. Board members noted the budget is tight and that, if funding gaps arise later, the district’s route would be to request additional support from the county.
Ending: With the approval, staff said they will begin preconstruction steps; the transcript shows the board expects ongoing cost monitoring and may seek alternative funding mechanisms for furnishings and equipment if construction costs approach estimates.