Mayor says FEMA mitigation award for Lighthouse Pier reduced after appeal; city to submit revised design
Summary
Biloxi's mayor told the council that appeals reduced the cost estimate for Lighthouse Pier repairs and that the city will submit a revised pier design for additional mitigation funds; MEMA support was noted for other Katrina infrastructure appeals.
Biloxi's mayor reported that the city's appeal of a federal grant award for Lighthouse Pier produced a lower mitigation cost estimate and that staff plan to submit a revised, mitigated pier design to request additional funding to rebuild with the desired materials.
The mayor said an initial FEMA figure of roughly $1.2 million was cut to $519,000 after mitigation analysis, and that appeals raised the total federal award (without mitigation) to about…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat