Heritage Park nearing exterior completion; staff outlines timeline, change orders and tree‑wrapping caution
Summary
City staff reported that Heritage Park construction is nearing exterior completion with a revised substantial completion target of Nov. 18 and final completion of Dec. 2; change orders and concerns about decorating a newly transplanted Christmas tree were discussed.
City project staff reported progress and upcoming change orders for Heritage Park and said the city expects the park exterior and landscaping to be ready for the annual Country Christmas celebration while interior work continues.
Nicole (staff member) said the contractor will request change orders for automatic fixtures in restrooms, removal of a concrete tree wall, and additional time for a roll‑up door and HVAC configuration issues. Staff…
Already have an account? Log in
Subscribe to keep reading
Unlock the rest of this article — and every article on Citizen Portal.
- Unlimited articles
- AI-powered breakdowns of topics, speakers, decisions, and budgets
- Instant alerts when your location has a new meeting
- Follow topics and more locations
- 1,000 AI Insights / month, plus AI Chat