Mayville approves site review and 50% match commitment for proposed EMS building, pending legal review
Summary
The council approved a site option behind the former Jopco building for a future EMS building, agreed to commit to 50% of project costs as a local match for a state grant application, and directed staff to obtain legal review about using parkland if necessary.
Get email alerts on the Ems Facility topic
No spam. Unsubscribe anytime.
The Mayville Common Council voted Tuesday to approve a proposed site for a future EMS building (behind the former Jopco building on Highway TW, sewer nearby) contingent on legal review and to commit to providing 50% of project costs as a local match to support a state capital grant application.
EMS leadership and staff reported a preferred site with sewer access but said water would require an extension. Council members emphasized the need for a legal opinion on whether parkland may be used for the project; staff were directed to consult the League of Wisconsin Municipalities— attorney and return with guidance.
Why it matters: The state capital grant program under discussion requires a site and a local commitment to qualify. Council agreed to a site pending legal counsel review and to a financial commitment equal to 50% of the project cost to enable the grant application; members noted the grant deadline is imminent.
Votes and follow-up
A motion to approve the site pending legal counsel and to commit to a 50% city match passed on roll calls (mover: Alderperson Olson; second: Alderperson Henkel; unanimous among those voting). Staff said a grant application must be filed by the end of the month and that building construction would not commence for a couple of years even if the grant is awarded.
Ending
Staff will obtain legal counsel on parkland-use constraints, finalize site details and submit the grant application with the city—s commitment to match 50% of the project cost if awarded.